Challenge
- Incomplete works and equipment requiring rehabilitation.
- Delayed availability of water and membranes required for testing.
- Damaged FCVs in Streams 2 and 3.

JIZAN · MBR STP · 3,000 m³/day
The project targeted restoration of an existing multi-system plant. The team worked on piping, instrumentation, protection, dosing and CIP systems, blower maintenance, panel rehabilitation, valve calibration and automatic-operation testing for critical equipment.